NOVEMBER PROGRESS REPORT

As at Nov-2024

Contractor: RABDIYA CONSTRUCTION
Project Start Date: 20/08/2024
Expected Construction Period: 18 months
Project Outline: Ongoing
14%

Progress Video

Progress Photos

Title : GROUND BREAKING
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Breaking ground for the project.
Completed.
Title : EXCAVATION AND EARTHWORKS
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Site Clearance.
Completed.
Setting Out.
Completed.
Excavation.
Completed.
Blinding Works.
Started.
Concrete Works.
Awaiting Commencement.
Walling.
Awaiting Commencement.
Back Filling.
Awaiting Commencement.
Casting of Ground Slab.
Awaiting Commencement.