SANTANA PROJECT UPDATE

PHASE 1A

Contractor: RABDIYA CONSTRUCTION
Project Start Date: 01/01/2025
Expected Construction Period: 24
Project Outline: ONGOING
70%

Progress Video

Progress Photos

Title : SUPER-STRUCTURE WORKS (1ST STOREY)
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Walling.
Completed.
Shuttering And Propping.
Completed.
Reinforcement Works.
Completed.
Mechanical Service.
Completed.
Electrical Service.
Completed.
Casting Of Slab.
Completed.
Title : SUPER-STRUCTURE WORKS (2ND STOREY)
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Walling.
Completed.
Shuttering And Propping.
Completed.
Reinforcement Works.
Completed.
Mechanical Service.
Completed.
Electrical Service.
Completed.
Casting Of Slab.
Completed.
Title : SUPER-STRUCTURE WORKS (3RD STOREY)
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Walling.
Completed.
Shuttering And Propping.
Completed.
Reinforcement Works.
Completed.
Mechanical Service.
Completed.
Electrical Service.
Completed.
Casting Of Slab.
Completed.
Title : SUPER-STRUCTURE WORKS (4TH STOREY)
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Walling.
Completed.
Shuttering And Propping.
Completed.
Reinforcement Works.
Completed.
Mechanical Service.
Completed.
Electrical Service.
Completed.
Casting Of Slab.
Completed.
Title : SUPER-STRUCTURE WORKS (5TH STOREY)
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Walling.
Completed.
Shuttering And Propping.
Completed.
Reinforcement Works.
Completed.
Mechanical Service.
Completed.
Electrical Service.
Completed.
Casting Of Slab.
Completed.
Title : SUPER-STRUCTURE WORKS (6TH STOREY)
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Walling.
Completed.
Shuttering And Propping.
Completed.
Reinforcement Works.
Completed.
Mechanical Service.
Completed.
Electrical Service.
Completed.
Casting Of Slab.
Completed.
Title : FINISHES
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Plaster Works.
70% Completed.
Painting Works.
10% Completed.
Tile Works.
Awaiting Commencement.
Joinery Works.
Awaiting Commencement.
Aluminum Works.
Awaiting Commencement.