FEBRUARY SITE PROGRESS

As at Feb-2025

Contractor: RABDIYA CONSTRUCTION
Project Start Date: 20/08/2024
Expected Construction Period: 18
Project Outline: ONGOING
18%

Progress Video

Progress Photos

Title : GROUND BREAKING
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Breaking Ground.
Completed.
Title : EXCAVATION AND EARTHWORKS
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Site Clearance.
Completed.
Setting Out.
Completed.
Excavation.
Completed.
Blinding Works.
Completed.
Reinforcement Work.
Completed.
Concrete Works.
Completed.
Walling.
Completed.
Back Filling.
Ongoing.
Casting Of Ground Slab
Awaiting Commencement.