SANTANA PROJECT-JUNE SITE UPDATES

As at Jun-2025

Contractor: RABDIYA CONSTRUCTION
Project Start Date: 20/08/2024
Expected Construction Period: 24
Project Outline: ONGOING
24%

Progress Video

Progress Photos

Title : EXCAVATION AND EARTHWORKS
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Breaking Ground.
Completed.
Site Clearance.
Completed.
Setting Out.
Completed.
Excavation.
Completed.
Blinding Works.
Completed.
Reinforcement Works.
Completed.
Concrete Works.
Completed.
Walling.
Completed.
Back Filling.
Completed.
Handcore Hand Packing.
Completed.
Laying of BRC and DPM.
Completed.
Slab Mechanical Service.
Completed.
Slab Electrical Service.
Completed.
Casting of Ground Slab.
Completed.
Title : SUPER-STRUCTURE WORKS (EARTHWORKS)
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Reinforcement Works.
Ongoing.
Mechanical Service.
Awaiting Commencement.
Electrical Service.
Awaiting Commencement.
Casting of Slab.
Awaiting Commencement.
Walling.
Awaiting Commencement.