APRIL SITE PROGRESS

As at Apr-2025

Contractor: RABDIYA CONSTRUCTION
Project Start Date: 20/08/2024
Expected Construction Period: 18
Project Outline: ONGOING
22%

Progress Video

Progress Photos

Title : GROUND BREAKING
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Breaking Ground.
Completed.
Title : EXCAVATION AND EARTHWORKS
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Site Clearance.
Completed.
Setting Out.
Completed.
Excavation.
Completed.
Blinding Works.
Completed.
Reinforcement Works.
Completed.
Concrete Works.
Completed.
Walling.
Completed.
Back Filling.
Completed.
Hardcore Hand Packing.
Ongoing.
Quarry Dust Blinding.
Awaiting Commencement.
Casting Of Ground Slabs.
Awaiting Commencement.