SANTANA PROJECT-AUGUST SITE UPDATES

As at Aug-2025

Contractor: RABDIYA CONSTRUCTION
Project Start Date: 20/08/2024
Expected Construction Period: 18
Project Outline: ONGOING
26%

Progress Video

Progress Photos

Title : EXCAVATION AND EARTHWORKS.
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Breaking Ground.
Completed.
Site Clearance.
Completed.
Setting Out.
Completed.
Excavation.
Completed.
Blinding Works.
Completed.
Reinforcement Works.
Completed.
Concrete Works.
Completed.
Walling.
Completed.
Back Filling.
Completed.
Hardcore Hand Packing.
Completed.
Laying of BRC and DPM.
Completed.
Slab Mechanical Service.
Completed.
Slab Electrical Service.
Completed.
Casting of Ground Slab.
Completed.
Title : SUPER-STRUCTURE WORKS (1ST STOREY).
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Walling.
Completed.
Shuttering and Propping.
Completed.
Reinforcement Works.
Completed.
Mechanical Service.
Completed.
Electrical Service.
Completed.
Casting of Slab.
Completed.
Title : SUPER-STRUCTURE WORKS (2ND STOREY).
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Walling.
Completed.
Shuttering and Propping.
Completed.
Reinforcement Works.
Completed.
Mechanical Service.
Ongoing.
Electrical Service.
Ongoing.
Casting of Slab.
Awaiting Commencement.