JANUARY PROGRESS REPORT

As at Jan-2025

Contractor: RABDIYA CONSTRUCTION
Project Start Date: 20/08/2024
Expected Construction Period: 18MONTHS
Project Outline: ONGOING
16%

Progress Video

Progress Photos

Title : GROUND BREAKING
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Breaking ground for the project.
Completed.
Title : EXCAVATION AND EARTHWORKS
CURRENT PROJECT ACTIVITY
PROJECT STATUS
Site Clearance
Completed.
Setting Out.
Completed.
Excavation.
Completed.
Blinding Works.
Completed.
Reinforcement Works.
Ongoing.
Concrete Works.
Awaiting Commencement.
Walling.
Awaiting Commencement.
Back Filling.
Awaiting Commencement.
Casting of Ground Slab.
Awaiting Commencement.